Project Cost Estimates

Land Acquisition Cost

The total project area is 1865 acres (755 Ha.). 740 acres in Bhawana village has been acquired at Rs. 7.33 lakhs per acre and Rs. 10,000 per acre has been paid towards compensation for structures.

For the same land, enhanced compensation and solatium has also been paid at Rs. 7.76 lakhs per acre, amounting to Rs. 56.76 crores, resulting in a total cost of Rs. 112.48 crores.

Break-up of Land Cost by Area

Cost figures in Rs. Crores
Particulars 740 Acres 324 Acres 800 Acres
Cost 54.98 48.75 161.00
Structure Compensation 0.74 - -
Enhanced Compensation 56.76 - -
Total 112.48 48.75 161.00

Cost of land acquired (March 1998): Rs. 161.23 Crores

Cost of land to be acquired (September 2000): Rs. 161.00 Crores

Services

The anticipated cost for provision of various services at the current price level in the industrial area is given below.

Anticipated Cost of Various Services
S. No. Description Cost in Rs. Crores
1. Power 288
2. Roads 162
3. Water Supply 100
4. Sewerage 64
5. Storm Water Management 58
6. Solid Waste Management 7
7. Fire Fighting 1
8. Horticulture & Landscaping 8
9. Services Building 12
10. Pre-operative Expenses 5
Total 705

Note: The above cost estimates represent the anticipated project expenditure at the relevant price levels indicated in the original project estimates. The figures are presented in Rs. Crores.